The joint venture Equinor-Polenergia (JVEP) and Sif have entered a capacity reservation agreement for the supply of 90 monopile foundations for JVEP’s Baltyk II and III offshore wind project in Poland.
 
The monopiles will be manufactured in 2025-2026 and have an estimated production volume of approximately 105 kton. Baltyk II and III are two offshore wind projects in the Polish Baltic Sea envisaging a total installed capacity of potentially 1.440 MW. Bałtyk II and III cover a combined area of approximately 240 square kilometers located between 22 km and 37 km from the coast. The water depths range from around 25 to 40 meters.
            
                
                


  
                
                